Nelson Airport Set to Begin $10 Million Apron Reconstruction
- 2024-10-31
• Essential infrastructure upgrades will improve safety and convenience for airlines and passengers
• Airport Perimeter Walkway partially closed for six months to enable construction
After years of planning, a full reconstruction of Nelson Airport’s apron will take place over the next six months to ensure a safe, high-quality environment for airport operators and passengers now and in the future.
The $10 million project will see the apron rebuilt in six stages, including replacement of an old concrete stormwater drain. The apron is the area of the airport where aircraft park, are loaded, unloaded and refuelled, and where passengers board and disembark.
Nelson Airport chief executive Brendan Cook says a full reconstruction has been planned for several years, and is essential to safeguard current and future airport operations.
“The existing apron is nearing the end of its life. It’s had a good run but we are at the point where continuing to extend its use through patch repairs is no longer practical or safe.”
Brendan said the need to reconstruct the entire area had provided an opportunity to implement design improvements that would improve safety and efficiency for airlines, as well as convenience for passengers.
“We’ve redesigned the stand arrangement (where aircraft park) for closer, more streamlined access from the terminal once works are complete. That’s a win for passengers, who can expect a more convenient and consistent experience boarding, regardless of which airline they choose to fly with.”
The project also provides the ability to expand the number of stands in future when extra capacity is needed.
The project will require the airport to close a 1.4-kilometre section of the Airport Perimeter Walkway from 11 November until works are complete. This closure is to allow construction vehicles to access the work site and transport excavated material to other airport sites.
Some material removed during the project will be re-used in other construction projects.
Through these methods, the project team aims to eliminate waste to landfill.
“The Airport Perimeter Walkway can still be accessed from Bolt Road as a return walk to and from the start of the construction management area. There will be signage at each end of the track alerting walkers,” Brendan says.
Airport visitors are advised to follow all signage and be aware there are likely to be some changes to carparking and pedestrian access to the terminal, as well as to their boarding and disembarking experience.
“It’s impossible to carry out a project of this size without any disruption, and we appreciate everyone’s patience and understanding over the next six months.”
Like other capital projects at Nelson Airport, including the new terminal development in 2019, the apron reconstruction work is funded by the airport company.